[Project] Remove the Weekend

milo -  
 Gilles -
Hello,

I am using Microsoft Project 2003!
I would like my tasks not to run on weekends! I want them to "skip" these 2 days and resume only on the following Monday!
Can anyone help me?

Thank you for your help.

Emilien.
Configuration: Windows XP Internet Explorer 6.0

1 réponse

Gilles
 
Hello

Check the type of calendar used in the PROJECT and PROJECT INFORMATION menu; normally the STANDARD calendar should be suitable. Ensure that this calendar has not been modified in the TOOLS menu and EDIT WORK TIME, where Saturday and Sunday are non-working days and should be "grayed out". The same applies for public holidays.
0