Managing a resource across multiple tasks - MS Project 2003
Angelo
-
innovaxion Posted messages 86 Status Member -
innovaxion Posted messages 86 Status Member -
Hello,
Configuration: Windows 2003 / Internet Explorer 8.0
A resource is assigned at 50% to 2 tasks: A and B
So my resource is fully utilized.
Task A will finish earlier.
How to configure MS Project so that as soon as Task A finishes, my resource is at 100% on Task B?
Thank you for your help
Angelo
Configuration: Windows 2003 / Internet Explorer 8.0
A resource is assigned at 50% to 2 tasks: A and B
So my resource is fully utilized.
Task A will finish earlier.
How to configure MS Project so that as soon as Task A finishes, my resource is at 100% on Task B?
Thank you for your help
Angelo
1 answer
-
Hello
There is only one way: manually assign the resource. For this, split the display, place the "task usage" display in the lower part, and manually enter the workload of the resource on the task day by day.
Best regards
--
Trainer on MS Project-
-
Hello
I just uploaded the explanation on my site with a screenshot. See the page https://www.innovaxion.net/cles-pour-ms-project-2010/project-2010-page-2/#ressources1
(Two tasks A and B and a resource Jean)
Best regards
-