Gantt project: One month delay between 2 tasks
ddur
-
Raymond PENTIER Posted messages 58219 Registration date Status Contributor Last intervention -
Raymond PENTIER Posted messages 58219 Registration date Status Contributor Last intervention -
Hello everyone,
I am currently building a Gantt chart using Gantt Project (version 2.8.9) and I am desperately looking for a way to offset two tasks using a finish/start link of one month.
So if the first task starts on 02/02/2020, the next task would start on 02/03/2020 (regardless of non-working days).
The delay field seems to only accept values in working days; I’ve tried entering 1 month/1M/1 month, but nothing works. Has anyone encountered this problem? What solution did you find?
Thank you,
David.
I am currently building a Gantt chart using Gantt Project (version 2.8.9) and I am desperately looking for a way to offset two tasks using a finish/start link of one month.
So if the first task starts on 02/02/2020, the next task would start on 02/03/2020 (regardless of non-working days).
The delay field seems to only accept values in working days; I’ve tried entering 1 month/1M/1 month, but nothing works. Has anyone encountered this problem? What solution did you find?
Thank you,
David.
1 answer
-
Hello.
There is confusion: "shift two tasks using a link start/end of a month", that does not exist!
You need to shift the start of the tasks by 30 days: In the properties of Task_2, in the Predecessors section, select the name Task_1, relationship Start-Start, delay 30.
- Note that the calendar can be modified to account for work on weekends!
--
Retirement is great! Especially in the Caribbean...
Raymond (INSA, AFPA)-
Hello Sir,
Thank you for your response,
is there any way to mix calendar day delays and working day delays?
For example, the contract I am about to sign states:
- signing of the contract on date T
- start of work 1 month later (implied 1 calendar month)
- synthesis of all networks by T+45 days (implied working days)
The problem is that date T is a variable and I do not know how to arrange the connections with delays in calendar and working days (as some months have 30 or 31 days).
Thank you,
David.
-