Man / day

Mr keita -  
 MR keita 1 -
Hello, I am requesting an explanation regarding the calculation of 120 men/day

Configuration: Windows / Edge 12.10240

2 answers

  1. Raymond PENTIER Posted messages 58216 Registration date   Status Contributor Last intervention   17 482
     
    It's true that it's complicated!
    That means it takes 120 men every day to do the work...
    If there are only 12 men available, it will take them 10 times longer!

    Retirement is nice! Especially in the Caribbean... :-)
    Raymond (INSA, AFPA, CF/R)
    2
    1. Mr keita
       
      Thank you Raymont
      here is my problem
      I have a terms of reference for an individual consultant asking me to make a financial proposal of 120 man-days
      the consultant's objective is to provide technical advice for the construction of three warehouses for a total of 120 man-days

      help me sir
      0
      1. Raymond PENTIER Posted messages 58216 Registration date   Status Contributor Last intervention   17 482 > Mr keita
         
        I am neither a consultant, nor a store builder, nor a technical advisor.
        Moreover, I did not understand the explanation above.
        I did everything I could, explaining the meaning of 120 man-days.
        It will be necessary to hire a real consultant...
        0