Inconsistencies in project duration and dates
AIARA
-
madmyke Posted messages 52304 Registration date Status Moderator Last intervention -
madmyke Posted messages 52304 Registration date Status Moderator Last intervention -
Hello,
I have an inconsistency between the duration of tasks and the associated dates.
For example: a date related to a predecessor in FD starts on the end date of the predecessor instead of starting the next day.
Likewise, when I enter 4 days (working days), the dates do not correspond to the 4 days between start and end.